EU Ordered to Pay Damages to Two Companies for Breach of Fundamental Right to Timely Court Proceedings
The EU General Court has ordered the EU to pay €50,000 in damages to two companies for the excessive and unjustified length of their proceedings before the General Court

In 2006, Gascogne Sack Deutschland and Gascogne sought to annul a European Commission decision fining them €13.2 million for participation in a cartel in the industrial plastic bags sector. However, it wasn't until November 2011, 5 years and 9 months later, that the EU General Court (GC) delivered its judgment and dismissed their actions.

The companies sought approximately €5 million in damages from the EU as compensation for both material and non-material harm caused by the inordinate length of the proceedings. In its first decision on this issue, the GC noted that non-contractual liability may be incurred by the EU when three cumulative conditions are fulfilled:

  • First, an EU institution must act unlawfully

    The GC held that a period of almost 6 years was not justified by the specific circumstances of the cases and breached the right to adjudication within a reasonable period, as enshrined in the EU Charter of Fundamental Rights. In reaching this conclusion, the GC considered the appropriate length of proceedings, bearing in mind the complexity of competition law and other parallel actions. The GC also uncovered a 20 month period of inactivity.

  • Second, actual damage must be suffered

    The GC accepted that bank costs in relation to the fine paid by Gascogne during the 20 months of inactivity amounted to actual damage. However, the GC rejected other claims of actual damage, including losses due to the payment of statutory interest applied to the Commission's fine.

  • Third, there must be a causal link between the unlawful conduct of the EU and the actual damage
    This condition was satisfied as bank costs paid by Gascogne during the 20 months of inactivity would not have arisen had the proceedings before the GC been more efficient.

The GC partially upheld the actions of the two companies, awarding damages of approximately €47,000 to Gascogne for material harm suffered due to the additional bank costs. The companies were also awarded €5,000 each for non-material harm caused by the excessive uncertainty created by the lengthy proceedings.

This is the first time that the EU courts have awarded damages for a breach of a company's fundamental right to timely court proceedings. The right is well established before the European Court of Human Rights, and the Irish Supreme Court recently recognised, in principle, that damages would be available for breach of the right (Nash v DPP).

Damages themselves are of course not the primary goal, and it is notable that the compensation awarded in this case fell well below the millions sought.  Recent reforms of the GC – including an increased number of judges and greater flexibility in the use of chambers – are intended to combat the excessive duration of proceedings and to allow the delivery of judgments within a reasonable time.

Contributed by Claire Waterson

Back to Legal News